January 15, 2024:
Stringing work of 500 kV Thung Song - Songkhla 3 (KM 105 - Songkhla 3)) Transmission Line (TILS-L-06)has been started.

December 13, 2023:
TSEC has successfully completed construction work for reconductoring of 230 kV Transmission Line with 3 phase two bundled 1386 MCM ACCCC conductor per phase towers from Hin Kong Power to Ravchaburi 2 (Job No. THKP-01-L01)

November 30, 2023:
Construction work of 230 kV Bang Lamung2 Junction - Bang Lamung2, 230 kV Rayong2 - Bang Lamung2 Transmission Line(TIPE-L-04)has been started.

August 15, 2023:
TSEC (Thailand) got Letter of Award of Contract for Invitation to Bid No. TIPE-L-04 from EGAT.

July 25, 2023:
TSEC (Thailand) is the lowest bidder of EGAT E-Bidding for 115 kV Hat Yai 1 - Hat Yai 2 Transmission Line and 230 kV Pathalung - Hat Yai 2 Transmission Line).

June 22, 2023:
TSEC (Thailand) is the lowest bidder of EGAT Job No. TS12-03-L04(Supply and Construction of 115 kV Wattana Nakhon (230kV) - Wattana Nakhon (115 kV) Transmission Line).

April 18, 2023:
TSEC (Thailand) is the lowest bidder of EGAT Bid No. TIPE-L-04(Supply and Construction of 230 kV Bang Lamung2 Junction - Bang Lamung2, 230 kV Rayong2 - Bang Lamung2 Transmission Line.

December 15, 2022:
Successful Completion of Transmission Line Upgrade Project(Photo Feature)

Ongoing Projects

230 kV Bang Lamung 2 Junction – Bang Lamung 2, 230 kV Rayong 2 – Bang Lamung 2 Junction Transmission Line (TIPE-L-04)

Supply and Construction of Transmission Line 230 kV Bang Lamung 2 Junction – Bang Lamung 2, 230 kV Rayong 2 – Bang Lamung 2 Junction, and Sectionalizing of 230 kV Rayong 2 – Ao Phai to Bang Lamung 2 Substation (TIPE-L-04)


 

  • Project Start : August 15, 2023

  • Expected Project Completion : August 15, 2025

115 kV Wattana Nakhon (230 kV) - Wattana Nakhon (115 kV)  Transmission Line (Job No. TS12-03-L04)

Supply and Construction of 115 kV Transmission Line with 3 phase two bundled 1272 MCM ACSR/GA conductor per phase, double circuit on self-supporting lattice steel towers from Wattana Nakhon (230 kV)  to Wattana Nakhon (115 kV)  (TS12-03-L04) and stringing works for Job No. TS12-L16-48 and TS12-L16-49. 


 

  • Project Start : July 10, 2023

  • Expected Project Completion : May 10, 2024

500 kV Thung Song - Songkhla 3 (KM 105 - Songkhla 3)) Transmission Line (TILS-L-06)

Supply and Stringing work of 500 kV 3 phase four bundled 1272 MCM ACSR conductor per phase, double circuit on self-supporting lattice steel towers for one section (approx. 52 km) of 500 kV Thung Song - Songkhla 3 Transmission Line (KM 105 - Songkhla 3).


 

  • Project Start : May 23, 2022

  • Expected Project Completion : July 23, 2024